HWY W FOURTH ST over COMB HAUL RD & CSX

1219 M SW OF D ST OFFICE · County 025, Massachusetts · Built 1918 · 2 Lanes · 3,500 vehicles/day

Structurally Deficient — One or more key components rated 4 (Poor) or below
Overall
Poor
Deck
5
Fair
Superstructure
4
Poor
Substructure
6
Satisfactory

Bridge Details

Structure #
B162033GPDOT634
Year Built
1918
Length
19.8 m (65 ft)
Max Span
17.4 m
Width
16.1 m (52.8 ft)
Lanes
2
Daily Traffic
3,500
Material
Steel
Design
Girder and Floorbeam System
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$2,091,000
Total Project Cost
$3,137,000