I-285 NB ON RAMP over I-285 RMP CB TO I-85 SB

2.3 MI E OF CHAMBLEE · County 089, Georgia · Built 1987 · 1 Lanes · 8,660 vehicles/day

Overall
Good
Deck
7
Good
Superstructure
7
Good
Substructure
7
Good

Bridge Details

Structure #
000000008902770
Year Built
1987
Length
156.1 m (512.1 ft)
Max Span
59.4 m
Width
10.1 m (33.1 ft)
Lanes
1
Daily Traffic
8,660
Material
Prestressed Concrete Continuous
Design
Box Beam or Girders - Single or Spread
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$1,455,000
Total Project Cost
$2,182,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.