ROUTE 8 over PROSPECT STREET
0.4 MI N OF I-95 · County 001, Connecticut · Built 1968 · 5 Lanes · 101,700 vehicles/day
Overall
Deck
6
Satisfactory
Superstructure
7
Good
Substructure
7
Good
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 6 | Satisfactory |
| Superstructure | 7 | Good |
| Substructure | 7 | Good |
Location
41.172833, -73.193097
This bridge is in worse condition than 31.3% of bridges in County 001. The average bridge in Connecticut is 0 years old; this one is 58 years old.
Nearby Bridges
ROUTE 8 SOUTHBOUND over ROUTE 8 SB RAMP 126
Built 1968
I-95 SB TR 805 over SOUTH AVE & WARREN ST
Built 1968
I-95 SB TR 804 over I-95 RAMP & LOCAL AVEs
Built 2002
INTERSTATE 95 over WARREN STREET
Built 1959
INTERSTATE 95 over MYRTLE AVENUE NO. 1
Built 1958
ROUTE 8 NORTHBOUND over WARREN ST& S FRONTAGE RD
Built 1968
INTERSTATE 95 over LAFAYETTE STREET NO. 2
Built 1959
ROUTE 8 NB & TR 80 over I-95 S FRONTAGE RD S.AVE
Built 1999
I-95 NB TR 806 over S. FRONTAGE RD & LAF. ST
Built 2000
ROUTE 8 NORTHBOUND over ROUTE 130 EAST BOUND
Built 1968
Bridge Details
- Structure #
- 03538
- Year Built
- 1968
- Length
- 20.4 m (66.9 ft)
- Max Span
- 18.9 m
- Width
- 34.4 m (112.9 ft)
- Lanes
- 5
- Daily Traffic
- 101,700
- Material
- Steel
- Design
- Stringer/Multi-beam or Girder
- Owner
- State Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- N/A
- Total Project Cost
- N/A
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.