HWY MINERAL ST over RR MBTA/BMRR
0.32 KM NE SUMMER AVE · County 017, Massachusetts · Built 1997 · 2 Lanes · 4,100 vehicles/day
Overall
Deck
7
Good
Superstructure
7
Good
Substructure
7
Good
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 7 | Good |
| Superstructure | 7 | Good |
| Substructure | 7 | Good |
Location
42.525681, -71.115886
This bridge is in worse condition than 9.4% of bridges in County 017. The average bridge in Massachusetts is 0 years old; this one is 29 years old.
Nearby Bridges
I 93 OFF RAMP over I 93 & NB ON RAMP
Built 2000
I 93 NB ON RAMP over I 93
Built 2000
ST129 LOWELL ST over RR MBTA/BMRR
Built 1958
HWY WEST ST over I 93
Built 1957
I 93 over HWY WEST ST
Built 1959
ST129 LOWELL ST over I 93
Built 1957
I 93 NB over RR MBTA/BMRR
Built 1958
I 95 /ST128 over HWY NORTH AVE
Built 1950
I 93 SB over RR MBTA/BMRR
Built 1958
I 95 /ST128 over RR MBTA/BMRR
Built 1950
Bridge Details
- Structure #
- R03001AD9DOT634
- Year Built
- 1997
- Length
- 36.4 m (119.4 ft)
- Max Span
- 13.2 m
- Width
- 10.7 m (35.1 ft)
- Lanes
- 2
- Daily Traffic
- 4,100
- Material
- Steel Continuous
- Design
- Stringer/Multi-beam or Girder
- Owner
- State Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $3,863,000
- Total Project Cost
- $5,795,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.