HWY BROWN ST over WATER HOOSIC RIVER

AT INT. WITH RIVER ST · County 003, Massachusetts · Built 1952 · 2 Lanes · 1,138 vehicles/day

Structurally Deficient — One or more key components rated 4 (Poor) or below
Overall
Serious
Deck
7
Good
Superstructure
2
Critical
Substructure
6
Satisfactory

Bridge Details

Structure #
N1400701GMUNNBI
Year Built
1952
Length
25.6 m (84 ft)
Max Span
25.1 m
Width
15.5 m (50.9 ft)
Lanes
2
Daily Traffic
1,138
Material
Steel
Design
Stringer/Multi-beam or Girder
Owner
City or Municipal Highway Agency
Last Inspected
N/A
Est. Improvement
$5,423,000
Total Project Cost
$8,135,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.