I 95 SB over ST 62 MAPLE ST

1.6 MI N ST114 · County 009, Massachusetts · Built 1972 · 4 Lanes · 38,090 vehicles/day

Structurally Deficient — One or more key components rated 4 (Poor) or below
Overall
Poor
Deck
6
Satisfactory
Superstructure
4
Poor
Substructure
5
Fair

Bridge Details

Structure #
D030332VHDOTNBI
Year Built
1972
Length
39 m (128 ft)
Max Span
18.9 m
Width
23.8 m (78.1 ft)
Lanes
4
Daily Traffic
38,090
Material
Steel
Design
Stringer/Multi-beam or Girder
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$6,181,000
Total Project Cost
$9,272,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.