HWY VIADUCT ST over HWY NORTHERN AVE
AT WORLD TRADE CENTER · County 025, Massachusetts · Built 1915 · 2 Lanes · 700 vehicles/day
Overall
Deck
6
Satisfactory
Superstructure
5
Fair
Substructure
5
Fair
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 6 | Satisfactory |
| Superstructure | 5 | Fair |
| Substructure | 5 | Fair |
Location
42.349983, -71.041564
This bridge is in worse condition than 55.1% of bridges in County 025. The average bridge in Massachusetts is 0 years old; this one is 111 years old.
Nearby Bridges
HWY VIADUCT ST over COMB CNGRSS&HAUL RD&CSX
Built 2002
HWY D ST over COMB HAUL RD & CSX
Built 2005
HWY SUMMER ST over HWY C ST
Built 2000
HWY SUMMER ST over COMB I90 RPS& HAUL &CSX
Built 2002
HWY SUMMER ST over HWY W SERVICE RD EXT
Built 2003
HWY SUMMER ST over HWY A ST
Built 1918
HWY SUMMER ST over WATER RESERVE CHANNEL
Built 1892
HWY SEAPORT BLVD over WATER FORT POINT CHANNEL
Built 1996
HWY CONGRESS ST over WATER FORT POINT CHANNEL
Built 1850
HWY SUMMER ST over WATER FORT POINT CHANNEL
Built 1899
Bridge Details
- Structure #
- B161974X5MPANBI
- Year Built
- 1915
- Length
- 34.5 m (113.2 ft)
- Max Span
- 15.8 m
- Width
- 18.5 m (60.7 ft)
- Lanes
- 2
- Daily Traffic
- 700
- Material
- Steel Continuous
- Design
- Girder and Floorbeam System
- Owner
- Other State Agencies
- Last Inspected
- N/A
- Est. Improvement
- $4,204,000
- Total Project Cost
- $6,307,000