EB CD TO IL 3 SB "" over UPRR
PIER D11-> PIER O-17 · County 163, Illinois · Built 1972 · 2 Lanes · 7,100 vehicles/day
Overall
Deck
6
Satisfactory
Superstructure
5
Fair
Substructure
6
Satisfactory
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 6 | Satisfactory |
| Superstructure | 5 | Fair |
| Substructure | 6 | Satisfactory |
Location
38.615411, -90.174006
This bridge is in worse condition than 74.8% of bridges in County 163. The average bridge in Illinois is 0 years old; this one is 54 years old.
Nearby Bridges
IL3NB TO 55/64WB "" over UPRR A B C IL 3 SB Ramp
Built 1969
WB CD TO IL3 SB ""0 over GROUND
Built 1971
I-55/64WB mainlne"" over UPRR IL 3 Ramp UPRR UPRR
Built 1995
I-55/64EB mainlne"" over UPRR IL 3 ramp UPRR UPRR
Built 1995
IL 3 NB Ramp ""F"" P over Abandoned Southern RR
Built 1971
Ramp to IL 3 SB ""E over Abandoned Southern RR
Built 1971
I-55/64 WB CD ""A"" over UPRR O2 B C H 4 ESL sts
Built 1968
IL 3 NB TO EB CD "" over I-55/64 EB CD ""D"" & UPRR
Built 1972
I-55/64 EB CD ""D"" over UPRR O2 8th9th10th Piggo
Built 1969
I-55/64 CD WB ""G"" over Trendley Avenue
Built 1968
Bridge Details
- Structure #
- 082020200000000
- Year Built
- 1972
- Reconstructed
- 2004
- Length
- 242 m (794 ft)
- Max Span
- 36.9 m
- Width
- 8.5 m (27.9 ft)
- Lanes
- 2
- Daily Traffic
- 7,100
- Material
- Steel Continuous
- Design
- Girder and Floorbeam System
- Owner
- State Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $1,556,000
- Total Project Cost
- $1,712,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.