ST 3 SB over US 3 SB CONNECTOR

0.25 MI SLY NH LINE · County 017, Massachusetts · Built 2004 · 3 Lanes · 42,200 vehicles/day

Overall
Good
Deck
7
Good
Superstructure
7
Good
Substructure
7
Good

Bridge Details

Structure #
T09022854DOTNBI
Year Built
2004
Length
41.9 m (137.5 ft)
Max Span
40.3 m
Width
24 m (78.7 ft)
Lanes
3
Daily Traffic
42,200
Material
Steel
Design
Stringer/Multi-beam or Girder
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$656,000
Total Project Cost
$985,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.