HWY ACCES BRG A over I 93 RAMPS CC & D
.15 K W OF [email protected] CON · County 025, Massachusetts · Built 2004 · 2 Lanes · 400 vehicles/day
Overall
Deck
7
Good
Superstructure
7
Good
Substructure
7
Good
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 7 | Good |
| Superstructure | 7 | Good |
| Substructure | 7 | Good |
Location
42.348633, -71.058256
This bridge is in worse condition than 1.6% of bridges in County 025. The average bridge in Massachusetts is 0 years old; this one is 22 years old.
Nearby Bridges
HWY ACCESS BRG B over I 93 RAMP KK
Built 2003
I 90 RAMP F over I 93 RMP KK &INFLD ACCS
Built 2004
HWY SO STA CONN over I 93 RAMPS CC KK D
Built 2004
HWY SO STA CONN over I 93 RAMPS CC KK D
Built 2004
HWY SO STA CONN over HWY FRONTAGE RD
Built 1995
I 93 RAMP X ACCS over OTHER RELIEF
Built 2005
I 93 RAMP K over OTHER RELIEF
Built 2004
I 93 RAMP E-SS over I 93 RAMP C
Built 2002
I 93 RAMP X over I 90 RAMP D & RAMP CC
Built 2004
HWY SO STA CONN over COMB MBTA & RELIEF
Built 1995
Bridge Details
- Structure #
- B166879QCDOTNBI
- Year Built
- 2004
- Length
- 20.8 m (68.2 ft)
- Max Span
- 19.7 m
- Width
- 9.3 m (30.5 ft)
- Lanes
- 2
- Daily Traffic
- 400
- Material
- Concrete
- Design
- Slab
- Owner
- State Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $807,000
- Total Project Cost
- $1,211,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.