HWY GRANITE AVE over WATER NEPONSET RIVER
MILTON TOWN LINE · County 025, Massachusetts · Built 1959 · 4 Lanes · 39,339 vehicles/day
Overall
Deck
5
Fair
Superstructure
5
Fair
Substructure
5
Fair
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 5 | Fair |
| Superstructure | 5 | Fair |
| Substructure | 5 | Fair |
Location
42.277481, -71.053297
This bridge is in worse condition than 55.1% of bridges in County 025. The average bridge in Massachusetts is 0 years old; this one is 67 years old.
Nearby Bridges
I 93 /US1/ST3 over WATER NEPONSET RIVER
Built 1954
I 93 /US1/ST3 over HWY GRANITE AVE
Built 1956
HWY ADAMS ST over TR RED LINE MATT CONN
Built 1886
HWY CEDAR GROVE over TR RED HSL
Built 1935
I 93 /US1/ST3 over HWY HALLET STREET
Built 1956
I 93 /US1/ST3 over OTHER PED/ BIKE PATH
Built 1956
I 93 /US1/ST3 over HWY THEATRE ACCESS RD
Built 1957
HWY MEDWAY ST over TR RED HSL
Built 1928
I 93 /US1/ST3 over HWY NEP AV/GALV/MRSY
Built 1955
ST 3 A/MORRSY BLV over COMB NEPONSET AVE&RIVER
Built 1970
Bridge Details
- Structure #
- B160223A3DOTNBI
- Year Built
- 1959
- Length
- 57 m (187 ft)
- Max Span
- 19.8 m
- Width
- 15.5 m (50.9 ft)
- Lanes
- 4
- Daily Traffic
- 39,339
- Material
- Steel
- Design
- Movable - Bascule
- Owner
- State Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $5,837,000
- Total Project Cost
- $8,756,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.