SR SPUR 6 over NS RAILROAD
2 MILES WEST OF AUSTELL · County 067, Georgia · Built 2000 · 4 Lanes · 11,900 vehicles/day
Overall
Deck
7
Good
Superstructure
7
Good
Substructure
7
Good
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 7 | Good |
| Superstructure | 7 | Good |
| Substructure | 7 | Good |
Location
33.820156, -84.653917
This bridge is in worse condition than 26.8% of bridges in County 067. The average bridge in Georgia is 0 years old; this one is 26 years old.
Nearby Bridges
US 278 / SR 6 over SWEETWATER CREEK
Built 1983
WESTSIDE ROAD over SWEETWATER CREEK
Built 1979
GARRETT ROAD over POWDER SPRINGS CREEK
Built 2009
AUSTEL POWDER SPGS over SWEETWATER CREEK
Built 1933
US 278 / SR 6 over POWDER SPRINGS CREEK
Built 1983
US 278 / SR 6 over NOR SOUTHERN RAILROAD
Built 1983
HIRAM-LITHIA SPRIN over SWEETWATER CREEK
Built 2009
CLAY ROAD over NOSES CREEK
Built 1995
JEFFERSON ST CONN over SR 5 CS 340 RAILROAD
Built 1998
PERKERSON MILL ROA over SWEETWATER CREEK
Built 1971
Bridge Details
- Structure #
- 000000006752430
- Year Built
- 2000
- Length
- 100.3 m (329.1 ft)
- Max Span
- 31.4 m
- Width
- 27.8 m (91.2 ft)
- Lanes
- 4
- Daily Traffic
- 11,900
- Material
- Steel
- Design
- Stringer/Multi-beam or Girder
- Owner
- State Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $1,987,000
- Total Project Cost
- $2,980,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.