I-90 over W-S RAMP RICHARD RD

0.2 E JCT I-405 · County 033, Washington · Built 1969 · 2 Lanes · 37,886 vehicles/day

Overall
Good
Deck
7
Good
Superstructure
7
Good
Substructure
7
Good

Bridge Details

Structure #
0008190D0000000
Year Built
1969
Length
56.1 m (184.1 ft)
Max Span
21.3 m
Width
11.1 m (36.4 ft)
Lanes
2
Daily Traffic
37,886
Material
Prestressed Concrete Continuous
Design
Stringer/Multi-beam or Girder
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$1,573,000
Total Project Cost
$3,146,000