NH120 PARK LOT PED over NHRR(ABD)
.1 MI FROM JCT RTE 4 · County 009, New Hampshire · Built 1969 · 2 Lanes · 5,317 vehicles/day
Structurally Deficient
— One or more key components rated 4 (Poor) or below
Overall
Deck
4
Poor
Superstructure
4
Poor
Substructure
5
Fair
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 4 | Poor |
| Superstructure | 4 | Poor |
| Substructure | 5 | Fair |
Location
43.642417, -72.254039
This bridge is in worse condition than 92.3% of bridges in County 009. The average bridge in New Hampshire is 0 years old; this one is 57 years old.
Nearby Bridges
US 4 NH 10 over MASCOMA RIVER
Built 1954
NH120 over MASCOMA RIVER
Built 1969
SPRING STREET over GREAT BROOK
Built 1953
NH120 over I-89
Built 1966
SLAYTON HILL ROAD over MASCOMA RIVER
Built 1972
BANK STREET EXT. over MASCOMA RIVER
Built 1985
MASCOMA STREET over I-89 NH 10
Built 1966
I-89 NH 10 SB over HEATER ROAD
Built 1966
I-89 NB over HEATER ROAD
Built 1966
US 4 MECHANIC ST over MASCOMA RIVER
Built 1977
Bridge Details
- Structure #
- 014401210011700
- Year Built
- 1969
- Length
- 8.5 m (27.9 ft)
- Max Span
- 7.3 m
- Width
- 18.7 m (61.4 ft)
- Lanes
- 2
- Daily Traffic
- 5,317
- Material
- Prestressed Concrete
- Design
- Slab
- Owner
- City or Municipal Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $272,000
- Total Project Cost
- $314,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.