HWY FRANKLIN AVE over HWY CSX ACCESS ROAD
1/4 MI N. GRAFTON ST · County 027, Massachusetts · Built 2013 · 2 Lanes · 9,613 vehicles/day
Overall
Deck
7
Good
Superstructure
8
Very Good
Substructure
7
Good
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 7 | Good |
| Superstructure | 8 | Very Good |
| Substructure | 7 | Good |
Location
42.260339, -71.788994
This bridge is in worse condition than 11.5% of bridges in County 027. The average bridge in Massachusetts is 0 years old; this one is 13 years old.
Nearby Bridges
I 290 EB over COMB 4 CITY STS & CSX
Built 1958
I 290 GRFTN ST ONR over HWY KEESE ST
Built 1960
I 290 SHWBY ST OFR over HWY MBTA PKNG ACCSS
Built 1960
I 290 WB over COMB 4 CITY STS & CSX
Built 1958
I 290 EB over HWY E CENTRAL ST
Built 1958
HWY HARRISON ST over I 290
Built 1958
I 290 WB over HWY E CENTRAL ST
Built 1958
I 290 & RAMPS over HWY PROSPECT ST
Built 1958
ST122 A/VERNON ST over I 290
Built 1959
HWY LAUREL ST over I 290
Built 1958
Bridge Details
- Structure #
- W44084BCYMUNNBI
- Year Built
- 2013
- Length
- 28.6 m (93.8 ft)
- Max Span
- 27.4 m
- Width
- 9.7 m (31.8 ft)
- Lanes
- 2
- Daily Traffic
- 9,613
- Material
- Steel
- Design
- Stringer/Multi-beam or Girder
- Owner
- State Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $1,827,000
- Total Project Cost
- $2,741,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.