HWY INGELL ST over WATER MILL RIVER

JUST S OF ST140 · County 005, Massachusetts · Built 2000 · 2 Lanes · 6,571 vehicles/day

Overall
Good
Deck
8
Very Good
Superstructure
8
Very Good
Substructure
8
Very Good

Bridge Details

Structure #
T01008AFDMUNNBI
Year Built
2000
Length
20.2 m (66.3 ft)
Max Span
19 m
Width
10.8 m (35.4 ft)
Lanes
2
Daily Traffic
6,571
Material
Prestressed Concrete
Design
Box Beam or Girders - Single or Spread
Owner
City or Municipal Highway Agency
Last Inspected
N/A
Est. Improvement
$1,636,000
Total Project Cost
$2,455,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.