ST 28 MCGRATH HWY over COMB SOM AVE EXT & MBTA

.1 MI S OF MEDFORD ST · County 017, Massachusetts · Built 1958 · 6 Lanes · 18,436 vehicles/day

Structurally Deficient — One or more key components rated 4 (Poor) or below
Overall
Poor
Deck
5
Fair
Superstructure
4
Poor
Substructure
4
Poor

Bridge Details

Structure #
S170244E3DOTNBI
Year Built
1958
Reconstructed
1983
Length
121.9 m (399.9 ft)
Max Span
38.4 m
Width
26.8 m (87.9 ft)
Lanes
6
Daily Traffic
18,436
Material
Steel
Design
Girder and Floorbeam System
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$39,008,000
Total Project Cost
$58,513,000