US 6 over ST138 RIVERSIDE AVE

WEST OF TAUNTON RIVER · County 005, Massachusetts · Built 2011 · 5 Lanes · 50,690 vehicles/day

Overall
Good
Deck
8
Very Good
Superstructure
8
Very Good
Substructure
8
Very Good

Bridge Details

Structure #
S16013AG0DOTNBI
Year Built
2011
Length
52.4 m (171.9 ft)
Max Span
22.4 m
Width
27.6 m (90.6 ft)
Lanes
5
Daily Traffic
50,690
Material
Prestressed Concrete Continuous
Design
Box Beam or Girders - Single or Spread
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$248,000
Total Project Cost
$373,000