ST 3 SB PLGRM HWY over ST228 HINGHAM ST

0.4 M S OF HINGHAM TL · County 023, Massachusetts · Built 1960 · 3 Lanes · 54,310 vehicles/day

Overall
Fair
Deck
7
Good
Superstructure
6
Satisfactory
Substructure
7
Good

Bridge Details

Structure #
R0800449GDOTNBI
Year Built
1960
Reconstructed
2007
Length
49.4 m (162.1 ft)
Max Span
23.2 m
Width
14.8 m (48.6 ft)
Lanes
3
Daily Traffic
54,310
Material
Steel
Design
Stringer/Multi-beam or Girder
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$3,639,000
Total Project Cost
$5,459,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.