I 90 EX 117 IN 13 over I 90
AT INTERCHANGE 13 · County 017, Massachusetts · Built 1957 · 3 Lanes · 45,000 vehicles/day
Structurally Deficient
— One or more key components rated 4 (Poor) or below
Overall
Deck
6
Satisfactory
Superstructure
6
Satisfactory
Substructure
4
Poor
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 6 | Satisfactory |
| Superstructure | 6 | Satisfactory |
| Substructure | 4 | Poor |
Location
42.312872, -71.384819
This bridge is in worse condition than 89.4% of bridges in County 017. The average bridge in Massachusetts is 0 years old; this one is 69 years old.
Nearby Bridges
I 90 EX 117 IN 13 over OTHER COCHITUATE TRAIL
Built 1957
I 90 EX 117 IN 13 over HWY SPEEN ST
Built 1957
I 90 EB over OTHER COCHITUATE TRAIL
Built 1957
I 90 WB over OTHER COCHITUATE TRAIL
Built 1957
HWY OLD CONN PTH over I 90
Built 1957
I 90 EX 117 IN 13 over ST 30 COCHITUATE RD
Built 1957
ST 30 COMM RD over I 90
Built 1957
I 90 EB over ST126 CONCORD ST
Built 1957
I 90 WB over ST126 CONCORD ST
Built 1957
HWY CONCORD ST over WATER SUDBURY RIVER
Built 1992
Bridge Details
- Structure #
- F070604P0DOTNBI
- Year Built
- 1957
- Reconstructed
- 1993
- Length
- 71.9 m (235.9 ft)
- Max Span
- 68.7 m
- Width
- 16.7 m (54.8 ft)
- Lanes
- 3
- Daily Traffic
- 45,000
- Material
- Steel
- Design
- Stringer/Multi-beam or Girder
- Owner
- State Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $7,806,000
- Total Project Cost
- $11,710,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.