HWY RAMP C over HWY POCASSET ST

RT79/RT138 TO I-195WB · County 005, Massachusetts · Built 2016 · 2 Lanes · 9,828 vehicles/day

Overall
Good
Deck
8
Very Good
Superstructure
8
Very Good
Substructure
8
Very Good

Bridge Details

Structure #
F02103BHADOTNBI
Year Built
2016
Length
21 m (68.9 ft)
Max Span
19.9 m
Width
9.6 m (31.5 ft)
Lanes
2
Daily Traffic
9,828
Material
Steel
Design
Stringer/Multi-beam or Girder
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$892,000
Total Project Cost
$1,339,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.