HWY ANAWAN ST over RR MACRR
MCRR MM · County 005, Massachusetts · Built 1904 · 2 Lanes · 4,784 vehicles/day
Overall
Deck
8
Very Good
Superstructure
8
Very Good
Substructure
7
Good
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 8 | Very Good |
| Superstructure | 8 | Very Good |
| Substructure | 7 | Good |
Location
41.702225, -71.161469
This bridge is in worse condition than 14% of bridges in County 005. The average bridge in Massachusetts is 0 years old; this one is 122 years old.
Nearby Bridges
HWY ST138 W FREX over COMB MACRR/QUECHAN RIVE
Built 1905
HWY WATER ST CON over RR MACRR
Built 2015
HWY WATER ST CON over OTHER ACCESS TO MACRR
Built 2015
I 195 over COMB ST79 & TAUNTON RIV
Built 1965
HWY RAMP A over HWY POCASSET ST
Built 2016
HWY RAMP G over COMB CENTRAL ST & MACRR
Built 2016
HWY RAMP C over HWY POCASSET ST
Built 2016
HWY CENTRAL ST over RR MACRR
Built 1904
HWY RAMP E over HWY POCASSET ST
Built 2016
HWY CENTRAL ST over WATER QUEQUECHAN RIVER
Built 1903
Bridge Details
- Structure #
- F02013407DOT634
- Year Built
- 1904
- Reconstructed
- 2015
- Length
- 14.1 m (46.3 ft)
- Max Span
- 11.8 m
- Width
- 13 m (42.7 ft)
- Lanes
- 2
- Daily Traffic
- 4,784
- Material
- Prestressed Concrete
- Design
- Slab
- Owner
- State Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $1,005,000
- Total Project Cost
- $1,508,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.