I 93 SB over OTHER RELIEF

ALBANY ST / FRONTAGE RD · County 025, Massachusetts · Built 1997 · 7 Lanes · 45,270 vehicles/day

Overall
Fair
Deck
6
Satisfactory
Superstructure
6
Satisfactory
Substructure
6
Satisfactory

Bridge Details

Structure #
B1665491EDOTNBI
Year Built
1997
Length
57.5 m (188.6 ft)
Max Span
18.4 m
Width
26.3 m (86.3 ft)
Lanes
7
Daily Traffic
45,270
Material
Prestressed Concrete Continuous
Design
Stringer/Multi-beam or Girder
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$7,501,000
Total Project Cost
$11,252,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.