I 93 RAMP SN over OTHER RELIEF

I93 RAMP SN · County 025, Massachusetts · Built 1999 · 1 Lanes · 34,914 vehicles/day

Overall
Fair
Deck
7
Good
Superstructure
7
Good
Substructure
6
Satisfactory

Bridge Details

Structure #
B165758YJDOTNBI
Year Built
1999
Length
38.1 m (125 ft)
Max Span
4 m
Width
7.9 m (25.9 ft)
Lanes
1
Daily Traffic
34,914
Material
Prestressed Concrete Continuous
Design
Slab
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$730,000
Total Project Cost
$1,096,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.