HWY MAPLE ST over WATER YOKUM BROOK

@ INTER. WITH MAIN ST · County 003, Massachusetts · Built 1928 · 2 Lanes · 129 vehicles/day

Overall
Fair
Deck
6
Satisfactory
Superstructure
6
Satisfactory
Substructure
7
Good

Bridge Details

Structure #
B03039038MUNNBI
Year Built
1928
Reconstructed
1983
Length
14.3 m (46.9 ft)
Max Span
13.4 m
Width
5.3 m (17.4 ft)
Lanes
2
Daily Traffic
129
Material
Concrete
Design
Tee Beam
Owner
Town or Township Highway Agency
Last Inspected
N/A
Est. Improvement
$517,000
Total Project Cost
$776,000