BAKER STREET over I-75 + I-75 RAMP

IN ATLANTA · County 121, Georgia · Built 1987 · 5 Lanes · 9,320 vehicles/day

Overall
Good
Deck
7
Good
Superstructure
7
Good
Substructure
7
Good

Bridge Details

Structure #
000000012106670
Year Built
1987
Length
119.2 m (391.1 ft)
Max Span
57 m
Width
88 m (288.7 ft)
Lanes
5
Daily Traffic
9,320
Material
Prestressed Concrete
Design
Stringer/Multi-beam or Girder
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$2,778,000
Total Project Cost
$4,166,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.