MCDANIEL STREET over NS RAILROAD (718067U)
IN ATLANTA · County 121, Georgia · Built 1988 · 4 Lanes · 7,440 vehicles/day
Overall
Deck
7
Good
Superstructure
7
Good
Substructure
7
Good
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 7 | Good |
| Superstructure | 7 | Good |
| Substructure | 7 | Good |
Location
33.744267, -84.404314
This bridge is in worse condition than 15.6% of bridges in County 121. The average bridge in Georgia is 0 years old; this one is 38 years old.
Nearby Bridges
MCDANIEL STREET over I-20
Built 1988
WHITEHALL STREET over NS RAILROAD (718069H)
Built 1990
PETERS STREET over SR 3(US 19) NORTHSIDE DR
Built 1953
I-20 over SR 3- NOR SOUTHERN RR
Built 1963
I-20- AND 2 RAMPS over M-9160 WINDSOR STREET
Built 1962
WHITEHALL STREET over M-9073 SPRING STREET
Built 1963
I-20 RMP TO I-75 over I-20R(WINDSOR ST)TO I20E
Built 1989
I-20 over SR 14- M-9124- NS RR.
Built 1962
SR 154 SPUR over I-20
Built 1992
SR 14 PETERS STRE over NS RAILROAD
Built 1935
Bridge Details
- Structure #
- 000000012104210
- Year Built
- 1988
- Length
- 24.7 m (81 ft)
- Max Span
- 14 m
- Width
- 20.8 m (68.2 ft)
- Lanes
- 4
- Daily Traffic
- 7,440
- Material
- Prestressed Concrete
- Design
- Box Beam or Girders - Multiple
- Owner
- City or Municipal Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $489,000
- Total Project Cost
- $734,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.