I-75 over I-75R TO SR247 PIERCE AV
IN NORTH MACON · County 021, Georgia · Built 2013 · 3 Lanes · 62,100 vehicles/day
Overall
Deck
7
Good
Superstructure
8
Very Good
Substructure
8
Very Good
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 7 | Good |
| Superstructure | 8 | Very Good |
| Substructure | 8 | Very Good |
Location
32.873797, -83.662317
This bridge is in worse condition than 41.2% of bridges in County 021. The average bridge in Georgia is 0 years old; this one is 13 years old.
Nearby Bridges
NORTH PIERCE AVE. over SAVAGE BRANCH
Built 1960
I-75 over UTILITY SEWER
Built 2014
RIVERVIEW STREET over I-75 @ 167.26N
Built 2011
OLD HOLTON ROAD over BOWMAN BRANCH
Built 1940
PIERCE AVE SR 247 over BOWMAN BRANCH
Built 1943
I-75 (NBL) over NS RAILROAD
Built 1966
I-75 (SBL) over NS RAILROAD
Built 1966
RED OAK DRIVE over I-75 @ 167.88N
Built 1992
I-75 SBL over I-16 RAMP/ NS R/R
Built 2020
I-75 over I-16 RAMP/ NS R/R
Built 2022
Bridge Details
- Structure #
- 000000002150680
- Year Built
- 2013
- Length
- 43 m (141.1 ft)
- Max Span
- 43 m
- Width
- 57.6 m (189 ft)
- Lanes
- 3
- Daily Traffic
- 62,100
- Material
- Prestressed Concrete
- Design
- Stringer/Multi-beam or Girder
- Owner
- State Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $12,506,000
- Total Project Cost
- $18,759,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.