ROUTE 8 SOUTHBOUND over ROUTE 130 EAST BOUND
0.6 MI N OF I-95 · County 001, Connecticut · Built 1968 · 3 Lanes · 45,600 vehicles/day
Overall
Deck
6
Satisfactory
Superstructure
6
Satisfactory
Substructure
6
Satisfactory
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 6 | Satisfactory |
| Superstructure | 6 | Satisfactory |
| Substructure | 6 | Satisfactory |
Location
41.1748, -73.19515
This bridge is in worse condition than 31.3% of bridges in County 001. The average bridge in Connecticut is 0 years old; this one is 58 years old.
Nearby Bridges
ROUTE 8 NORTHBOUND over ROUTE 130 EAST BOUND
Built 1968
ROUTE 8 NORTHBOUND over JOHN STREET
Built 1968
ROUTE 8 SOUTHBOUND over JOHN STREET
Built 1968
ROUTE 8 SOUTHBOUND over SR 700 FAIRFIELD AV
Built 1968
ROUTE 8 NORTHBOUND over SR 700 FAIRFIELD AVE.
Built 1969
ROUTE 8 NORTHBOUND over ROUTE 8 SB RAMP 126
Built 1968
ROUTE 8 SOUTHBOUND over ROUTE 8 SB RAMP 126
Built 1968
ROUTE 8 over PROSPECT STREET
Built 1968
ROUTE 8 NB RAMP 12 over ROUTE 8 NB RAMP 127
Built 1968
I-95 SB TR 804 over I-95 RAMP & LOCAL AVEs
Built 2002
Bridge Details
- Structure #
- 03539B
- Year Built
- 1968
- Reconstructed
- 1995
- Length
- 22.9 m (75.1 ft)
- Max Span
- 22.3 m
- Width
- 16 m (52.5 ft)
- Lanes
- 3
- Daily Traffic
- 45,600
- Material
- Steel
- Design
- Stringer/Multi-beam or Girder
- Owner
- State Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- N/A
- Total Project Cost
- N/A
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.