S 156TH WAY over MILLER CREEK

0.5 MI S OF SR-518 · County 033, Washington · Built 2005 · 2 Lanes · 10,150 vehicles/day

Overall
Good
Deck
7
Good
Superstructure
7
Good
Substructure
7
Good

Condition Ratings

ComponentRatingDescription
Deck 7 Good
Superstructure 7 Good
Substructure 7 Good

Location

47.463389, -122.322222

This bridge is in worse condition than 12.8% of bridges in County 033. The average bridge in Washington is 0 years old; this one is 21 years old.

Nearby Bridges

Bridge Details

Structure #
087291000000000
Year Built
2005
Length
14.9 m (48.9 ft)
Max Span
14.9 m
Width
16.1 m (52.8 ft)
Lanes
2
Daily Traffic
10,150
Material
Concrete
Design
Slab
Owner
City or Municipal Highway Agency
Last Inspected
N/A
Est. Improvement
$466,000
Total Project Cost
$931,000