C2007 over VERMONT RAILWAY

0.18 MI TO JCT W CL2 TH8 · County 007, Vermont · Built 1966 · 1 Lanes · 1,900 vehicles/day

Overall
Fair
Deck
6
Satisfactory
Superstructure
6
Satisfactory
Substructure
6
Satisfactory

Bridge Details

Structure #
100403000204031
Year Built
1966
Reconstructed
1973
Length
24.7 m (81 ft)
Max Span
24.1 m
Width
5.2 m (17.1 ft)
Lanes
1
Daily Traffic
1,900
Material
Steel
Design
Stringer/Multi-beam or Girder
Owner
Town or Township Highway Agency
Last Inspected
N/A
Est. Improvement
$488,000
Total Project Cost
$538,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.