POST OAK RUN over SULFUR BRANCH
1.3 MI W OF HIGH MEADOW · County 339, Texas · Built 2000 · 2 Lanes · 400 vehicles/day
Overall
Culvert
6
Satisfactory
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Culvert | 6 | Satisfactory |
Location
30.167592, -95.719503
This bridge is in worse condition than 78.1% of bridges in County 339. The average bridge in Texas is 0 years old; this one is 26 years old.
Nearby Bridges
CHAMPIONS DRIVE over SULFUR BRANCH
Built 2004
MEADOW WOOD GREEN over DAVIS BRANCH
Built 2000
Old Coach Road over Lake Apache
Built 2023
OLD COACH RD over LAKE APACHE SPILLWAY
Built 1963
FM 1774 over DITCH
Built 2020
STAGECOACH RD over LAKE HARDIN BRANCH
Built 2011
WALNUT CREEK RD over SULPHUR BRANCH
Built 1996
FM 1774 over DECKER BRANCH
Built 2020
WALNUT CREEK RD over WALNUT CREEK
Built 1987
VETERANS RD over ARNOLD BRANCH
Built 2003
Bridge Details
- Structure #
- 121700A01037030
- Year Built
- 2000
- Length
- 11 m (36.1 ft)
- Max Span
- 3.4 m
- Lanes
- 2
- Daily Traffic
- 400
- Material
- Steel
- Design
- Culvert
- Owner
- County Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $0
- Total Project Cost
- $0
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.