NH 28 NH109 over SMITH RIVER

3.5 MI FROM ALTON TL · County 003, New Hampshire · Built 1935 · 2 Lanes · 8,809 vehicles/day

Overall
Good
Deck
7
Good
Superstructure
7
Good
Substructure
7
Good

Bridge Details

Structure #
028301120011000
Year Built
1935
Reconstructed
2006
Length
10.5 m (34.4 ft)
Max Span
9.5 m
Width
15 m (49.2 ft)
Lanes
2
Daily Traffic
8,809
Material
Prestressed Concrete
Design
Slab
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$272,000
Total Project Cost
$314,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.