NH109 over SMITH RIVER

3.5 MI SE TUFTONBORO TL · County 003, New Hampshire · Built 1900 · 2 Lanes · 7,358 vehicles/day

Overall
Good
Deck
8
Very Good
Superstructure
8
Very Good
Substructure
7
Good

Bridge Details

Structure #
028301000011200
Year Built
1900
Reconstructed
1995
Length
9.4 m (30.8 ft)
Max Span
7.9 m
Width
20.3 m (66.6 ft)
Lanes
2
Daily Traffic
7,358
Material
Prestressed Concrete
Design
Slab
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$272,000
Total Project Cost
$314,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.