MCDONALD LAKE RD over PABLO FEEDER CANAL 077
7M NE ST IGNATIUS · County 047, Montana · Built 2004 · 2 Lanes · 100 vehicles/day
Overall
Deck
7
Good
Superstructure
7
Good
Substructure
7
Good
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 7 | Good |
| Superstructure | 7 | Good |
| Substructure | 7 | Good |
Location
47.413233, -114.017256
This bridge is in worse condition than 28.4% of bridges in County 047. The average bridge in Montana is 0 years old; this one is 22 years old.
Nearby Bridges
EAGLE PASS TRAIL over PABLO FEEDER CANAL 104
Built 1977
HILLSIDE ROAD over POST CREEK
Built 2023
MCDONALD LAKE RD over POST CREEK 078
Built 2015
DELANEY WAY over POST CREEK 074
Built 2017
EAGLE PASS TRAIL over S KICKING HORSE RES 010
Built 1991
EAST POST CREEK RD over POST CREEK 080
Built 2022
IRR - US 93 over POST CREEK
Built 1933
IRR - US 93 over NINE PIPE RESERVOIR
Built 1933
FISH HATCHERY RD over POST CREEK 075
Built 1920
ALLISON RD over PABLO FEEDER CANAL 046
Built 1960
Bridge Details
- Structure #
- L24352003+09001
- Year Built
- 2004
- Length
- 12.3 m (40.4 ft)
- Max Span
- 11.3 m
- Width
- 7.5 m (24.6 ft)
- Lanes
- 2
- Daily Traffic
- 100
- Material
- Steel
- Design
- Stringer/Multi-beam or Girder
- Owner
- County Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- N/A
- Total Project Cost
- N/A
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.