I 290 EB over ST 12 HOPE AVE
.2 MI E OF AUBURN T.L. · County 027, Massachusetts · Built 1965 · 4 Lanes · 48,961 vehicles/day
Overall
Deck
6
Satisfactory
Superstructure
6
Satisfactory
Substructure
7
Good
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 6 | Satisfactory |
| Superstructure | 6 | Satisfactory |
| Substructure | 7 | Good |
Location
42.232494, -71.823206
This bridge is in worse condition than 30.9% of bridges in County 027. The average bridge in Massachusetts is 0 years old; this one is 61 years old.
Nearby Bridges
I 290 WB over ST 12 HOPE AVE
Built 1965
I 290 EB over RR PWRR
Built 1966
I 290 WB over RR PWRR
Built 1966
I 290 over WATER KETTLE BROOK
Built 1965
I 290 RAMP B over HWY SOUTHBRIDGE ST
Built 1966
I 290 EB over HWY SOUTHBRIDGE ST
Built 1966
I 290 WB over HWY SOUTHBRIDGE ST
Built 1966
HWY WEBSTER ST over WATER LEESVILLE PD OTLT
Built 1935
HWY FREMONT ST over WATER MIDDLE RIVER
Built 1984
I 290 EB over HWY SWORD ST
Built 1965
Bridge Details
- Structure #
- W441031RJDOTNBI
- Year Built
- 1965
- Length
- 33.8 m (110.9 ft)
- Max Span
- 32.6 m
- Width
- 18.7 m (61.4 ft)
- Lanes
- 4
- Daily Traffic
- 48,961
- Material
- Steel
- Design
- Stringer/Multi-beam or Girder
- Owner
- State Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $4,128,000
- Total Project Cost
- $6,193,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.