HWY BRIDGE ST over WATER MILL RIVER

200 S OF RTE 9 · County 015, Massachusetts · Built 1918 · 2 Lanes · 1,400 vehicles/day

Structurally Deficient — One or more key components rated 4 (Poor) or below
Overall
Serious
Deck
7
Good
Superstructure
7
Good
Substructure
3
Serious

Bridge Details

Structure #
W360110FEMUNNBI
Year Built
1918
Reconstructed
1968
Length
27.4 m (89.9 ft)
Max Span
12.8 m
Width
11.1 m (36.4 ft)
Lanes
2
Daily Traffic
1,400
Material
Steel Continuous
Design
Stringer/Multi-beam or Girder
Owner
Town or Township Highway Agency
Last Inspected
N/A
Est. Improvement
$5,349,000
Total Project Cost
$8,024,000