I 195 WB over HWY MAIN ST

3.6 M E OF RTE 105 · County 023, Massachusetts · Built 1970 · 2 Lanes · 13,786 vehicles/day

Overall
Fair
Deck
7
Good
Superstructure
6
Satisfactory
Substructure
7
Good

Bridge Details

Structure #
W0605248EDOTNBI
Year Built
1970
Length
27.1 m (88.9 ft)
Max Span
25.6 m
Width
13.8 m (45.3 ft)
Lanes
2
Daily Traffic
13,786
Material
Prestressed Concrete
Design
Box Beam or Girders - Single or Spread
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$502,000
Total Project Cost
$754,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.