HWY COLUMBUS AVE over WATER W BR HOUSATONIC R

AT DEWEY AVE. · County 003, Massachusetts · Built 1996 · 2 Lanes · 4,526 vehicles/day

Overall
Fair
Deck
7
Good
Superstructure
6
Satisfactory
Substructure
7
Good

Bridge Details

Structure #
P10037AGEMUNNBI
Year Built
1996
Length
20.7 m (67.9 ft)
Max Span
19.7 m
Width
14.5 m (47.6 ft)
Lanes
2
Daily Traffic
4,526
Material
Prestressed Concrete
Design
Box Beam or Girders - Single or Spread
Owner
City or Municipal Highway Agency
Last Inspected
N/A
Est. Improvement
$1,080,000
Total Project Cost
$1,621,000