ST125 BRIDGE ST over RR BMRR (ABANDONED)

.16 KM S MERRIMAC RIVER · County 009, Massachusetts · Built 1850 · 2 Lanes · 27,200 vehicles/day

Structurally Deficient — One or more key components rated 4 (Poor) or below
Overall
Serious
Deck
2
Critical
Superstructure
2
Critical
Substructure
5
Fair

Bridge Details

Structure #
H12025310DOTNBI
Year Built
1850
Reconstructed
1968
Length
9.8 m (32.2 ft)
Max Span
9.8 m
Width
22.1 m (72.5 ft)
Lanes
2
Daily Traffic
27,200
Material
Prestressed Concrete
Design
Box Beam or Girders - Multiple
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$4,462,000
Total Project Cost
$6,694,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.