HWY COUNTRY CLUB over RR MACRR

.2 MI WEST OF N. MAIN ST · County 005, Massachusetts · Built 2016 · 2 Lanes · 714 vehicles/day

Overall
Good
Deck
8
Very Good
Superstructure
8
Very Good
Substructure
8
Very Good

Condition Ratings

ComponentRatingDescription
Deck 8 Very Good
Superstructure 8 Very Good
Substructure 8 Very Good

Location

41.753181, -71.123967

This bridge is in worse condition than 7.8% of bridges in County 005. The average bridge in Massachusetts is 0 years old; this one is 10 years old.

Nearby Bridges

Bridge Details

Structure #
F02091BMFDOTNBI
Year Built
2016
Length
25.5 m (83.7 ft)
Max Span
24.3 m
Width
11.8 m (38.7 ft)
Lanes
2
Daily Traffic
714
Material
Steel
Design
Stringer/Multi-beam or Girder
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$1,238,000
Total Project Cost
$1,858,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.