I 93 RAMP NS over OTHER RELIEF

I93 RAMP NS · County 025, Massachusetts · Built 1999 · 1 Lanes · 31,810 vehicles/day

Overall
Fair
Deck
6
Satisfactory
Superstructure
6
Satisfactory
Substructure
6
Satisfactory

Bridge Details

Structure #
B165748YQDOTNBI
Year Built
1999
Length
12.5 m (41 ft)
Max Span
4 m
Width
7.4 m (24.3 ft)
Lanes
1
Daily Traffic
31,810
Material
Prestressed Concrete
Design
Slab
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$244,000
Total Project Cost
$367,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.