HWY CHELSEA ST over WATER LITTLE MYSTIC CHAN

UNDER TOBIN AT MORAN TERM · County 025, Massachusetts · Built 1982 · 2 Lanes · 4,008 vehicles/day

Overall
Fair
Deck
6
Satisfactory
Superstructure
5
Fair
Substructure
7
Good

Bridge Details

Structure #
B163842CQMUNNBI
Year Built
1982
Length
116.7 m (382.9 ft)
Max Span
44.8 m
Width
12.6 m (41.3 ft)
Lanes
2
Daily Traffic
4,008
Material
Steel Continuous
Design
Stringer/Multi-beam or Girder
Owner
City or Municipal Highway Agency
Last Inspected
N/A
Est. Improvement
$9,571,000
Total Project Cost
$14,357,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.