ST129 SALEM RD over WATER SHAWSHEEN RIVER
0.75 MI E SALEM & BALDWIN · County 017, Massachusetts · Built 1932 · 2 Lanes · 10,600 vehicles/day
Overall
Superstructure
5
Fair
Substructure
6
Satisfactory
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Superstructure | 5 | Fair |
| Substructure | 6 | Satisfactory |
Location
42.568061, -71.215103
This bridge is in worse condition than 49.9% of bridges in County 017. The average bridge in Massachusetts is 0 years old; this one is 94 years old.
Nearby Bridges
HWY GEO BROWN ST over RR MBTA/BMRR
Built 2005
HWY NICHOLS ST over RR MBTA/BMRR
Built 1968
HWY LAKE ST over RR MBTA/BMRR
Built 1986
HWY ANDOVER RD over RR MBTA/BMRR
Built 2006
HWY GRAY ST over RR MBTA/BMRR
Built 1996
ST 38 MAIN ST over WATER SHAWSHEEN RIVER
Built 1997
ST129 RICHMOND RD over WATER MIDDLESEX CANAL
Built 1974
ST129 RICHMOND RD over RR MBTA/BMRR
Built 1973
HWY MILLERS FARM over WATER UNKNOWN
Built 1995
HWY BRIDGE ST over WATER SHAWSHEEN RIVER
Built 1979
Bridge Details
- Structure #
- B120082KRDOTNBI
- Year Built
- 1932
- Length
- 6.4 m (21 ft)
- Max Span
- 6.4 m
- Width
- 12.2 m (40 ft)
- Lanes
- 2
- Daily Traffic
- 10,600
- Material
- Masonry
- Design
- Arch - Deck
- Owner
- State Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $555,000
- Total Project Cost
- $833,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.