2300 EAST ROAD over SALMON CANAL LATERAL #2

1.8 S. 1.0 W. HOLLISTER · County 083, Idaho · Built 1971 · 2 Lanes · 90 vehicles/day

Overall
Fair
Deck
7
Good
Superstructure
5
Fair
Substructure
6
Satisfactory

Condition Ratings

ComponentRatingDescription
Deck 7 Good
Superstructure 5 Fair
Substructure 6 Satisfactory

Location

42.325642, -114.594253

This bridge is in worse condition than 65.9% of bridges in County 083. The average bridge in Idaho is 0 years old; this one is 55 years old.

Nearby Bridges

Bridge Details

Structure #
000000000025635
Year Built
1971
Length
17.7 m (58.1 ft)
Max Span
8.5 m
Width
8.7 m (28.5 ft)
Lanes
2
Daily Traffic
90
Material
Prestressed Concrete
Design
Tee Beam
Owner
Other Local Agencies
Last Inspected
N/A
Est. Improvement
$379,000
Total Project Cost
$569,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.