2300 EAST ROAD over BIG WOOD RIVER
3.8 N. 3.8 E. GOODING · County 047, Idaho · Built 1930 · 2 Lanes · 20 vehicles/day
Overall
Deck
6
Satisfactory
Superstructure
5
Fair
Substructure
6
Satisfactory
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 6 | Satisfactory |
| Superstructure | 5 | Fair |
| Substructure | 6 | Satisfactory |
Location
42.992094, -114.636528
This bridge is in worse condition than 65% of bridges in County 047. The average bridge in Idaho is 0 years old; this one is 96 years old.
Nearby Bridges
1375 SOUTH ROAD over CANAL
Built 1930
2300 EAST ROAD over N.GOODING MAIN CANAL
Built 1985
STC2781;1300 S. RD over THORN CREEK
Built 1955
1400 SOUTH ROAD over POORMAN DITCH
Built 2024
2400 EAST ROAD over GOODING MAIN CANAL
Built 1930
2500 EAST ROAD over GOODING MAIN CANAL
Built 1930
SH 46 over NRTH GOODING MAIN CNL
Built 1983
620 NORTH ROAD over MILNER GOODING CANAL
Built 1960
1775 SOUTH ROAD over LITTLE WOOD RIVER
Built 1926
2300 EAST ROAD over LITTLE WOOD RIVER
Built 1930
Bridge Details
- Structure #
- 000000000024440
- Year Built
- 1930
- Reconstructed
- 2003
- Length
- 29 m (95.1 ft)
- Max Span
- 27.4 m
- Width
- 6.6 m (21.7 ft)
- Lanes
- 2
- Daily Traffic
- 20
- Material
- Steel
- Design
- Truss - Thru
- Owner
- Other Local Agencies
- Last Inspected
- N/A
- Est. Improvement
- $554,000
- Total Project Cost
- $832,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.