STC2781;1300 S. RD over THORN CREEK
5.0 N. 5.1 E. GOODING · County 047, Idaho · Built 1955 · 2 Lanes · 360 vehicles/day
Structurally Deficient
— One or more key components rated 4 (Poor) or below
Overall
Deck
5
Fair
Superstructure
6
Satisfactory
Substructure
2
Critical
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 5 | Fair |
| Superstructure | 6 | Satisfactory |
| Substructure | 2 | Critical |
Location
43.011214, -114.613336
This bridge is in worse condition than 98.8% of bridges in County 047. The average bridge in Idaho is 0 years old; this one is 71 years old.
Nearby Bridges
2400 EAST ROAD over GOODING MAIN CANAL
Built 1930
2300 EAST ROAD over N.GOODING MAIN CANAL
Built 1985
2500 EAST ROAD over GOODING MAIN CANAL
Built 1930
1375 SOUTH ROAD over CANAL
Built 1930
620 NORTH ROAD over MILNER GOODING CANAL
Built 1960
2300 EAST ROAD over BIG WOOD RIVER
Built 1930
850 WEST ROAD over EAST MAIN CANAL
Built 2024
720 NORTH ROAD over MILNER GOODING CANAL
Built 2021
1400 SOUTH ROAD over POORMAN DITCH
Built 2024
SH 46 over NRTH GOODING MAIN CNL
Built 1983
Bridge Details
- Structure #
- 000000000019525
- Year Built
- 1955
- Reconstructed
- 1976
- Length
- 21.9 m (71.9 ft)
- Max Span
- 7.3 m
- Width
- 8.2 m (26.9 ft)
- Lanes
- 2
- Daily Traffic
- 360
- Material
- Steel
- Design
- Stringer/Multi-beam or Girder
- Owner
- Other Local Agencies
- Last Inspected
- N/A
- Est. Improvement
- $476,000
- Total Project Cost
- $714,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.