I-185 NBL over NS RAILROAD

NW COLUMBUS · County 215, Georgia · Built 1977 · 3 Lanes · 54,600 vehicles/day

Overall
Good
Deck
7
Good
Superstructure
8
Very Good
Substructure
7
Good

Bridge Details

Structure #
000000021500740
Year Built
1977
Length
94.2 m (309.1 ft)
Max Span
36.9 m
Width
18.7 m (61.4 ft)
Lanes
3
Daily Traffic
54,600
Material
Steel Continuous
Design
Stringer/Multi-beam or Girder
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$1,537,000
Total Project Cost
$2,305,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.