US 19 over 400 SOUTH RAMP

5.8 MI SOUTH OF ROSWELL · County 121, Georgia · Built 2021 · 5 Lanes · 50,570 vehicles/day

Overall
Good
Deck
8
Very Good
Superstructure
8
Very Good
Substructure
8
Very Good

Bridge Details

Structure #
000000012154160
Year Built
2021
Length
41.1 m (134.8 ft)
Max Span
41.1 m
Width
28.3 m (92.8 ft)
Lanes
5
Daily Traffic
50,570
Material
Concrete
Design
Stringer/Multi-beam or Girder
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$12,062,000
Total Project Cost
$18,093,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.