I-75 over OCMULGEE RIVER TRIB
IN EAST CENTRAL MACON · County 021, Georgia · Built 1967 · 8 Lanes · 82,900 vehicles/day
Overall
Culvert
7
Good
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Culvert | 7 | Good |
Location
32.846272, -83.642386
This bridge is in worse condition than 41.2% of bridges in County 021. The average bridge in Georgia is 0 years old; this one is 59 years old.
Nearby Bridges
WALNUT STREET EXT over I-75
Built 2019
US 41 RAMP over I-75 RAMP TO I-16 EAST
Built 2019
US 23/ SR 87 over I-75
Built 2020
I-75 over OCMULGEE RIVER TRIB
Built 1967
US 41 BUS SBL/SR 1 over I-75 (EXIT 164) @164.02
Built 1968
US 41 BUS NBL/SR 1 over I-75 (EXIT 164)@164.12
Built 1968
I-16 over I-75
Built 2022
I-16 RAMP over I-75
Built 2021
I-75 RAMP/ I-16 EB over NORFOLK SOUTHERN R/R
Built 2021
I-16 EBL over OCMULGEE RIVER
Built 2021
Bridge Details
- Structure #
- 000000002100930
- Year Built
- 1967
- Reconstructed
- 2019
- Length
- 9.8 m (32.2 ft)
- Max Span
- 2.7 m
- Lanes
- 8
- Daily Traffic
- 82,900
- Material
- Concrete
- Design
- Culvert
- Owner
- State Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $319,000
- Total Project Cost
- $479,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.